Avonmouth Waste Processing Plant​

Avonmouth Waste Processing Plant

Client: Bristol Waste Company

The project is being developed in partnership with our client Bristol Waste Company and SLR Consulting, following on from the successful delivery of BWC’s Hartcliffe Way Household Reuse and Recycling Centre. Scope of works includes:

  • Construction of a new 2,160m2 (23,250sq.ft.) waste processing plant building, structural steel frame and cladding on piled RC foundations, and associated external infrastructure works.
  • Storm water and foul water with filter drainage installations site wide, including connections to existing SW and FW drainage.
  • Installation of a 1000m³ storm water attenuation tank and associated interceptor units.
  • Service ducting installations.
  • Construction of external reinforced concrete hard-standings and access roads, with associated perimeter kerbing and tarmac footways.
  • Electrical installations to the WPP building, including solar PV roof-mounted system.

 

The WPP Building will be prepared to accept a fully automated Materials Recycling Facility

Encon's Civil Engineering Sectors

Learn more about the sectors we works in and see examples of our latest projects!

Walpole-Anaerobic-2

Waste to Energy

MK BridgewaterGateway-56

Infrastructure

Rover-Way-12

Industrial

default

Environment

DCIM100MEDIADJI_0026.JPG

Heritage & Restoration